INFORMATION OF ELECTRICITY NETWORK RELIABILITY IMPROVEMENT PT. PLN (PERSERO) UP3 BANYUWANGI |
||
---|---|---|
Day / Date | : | Thursday, 24 October 2019 |
Jam | : | 09:00 - 16:00 WIB |
Location of Padam | : | Ds. Sidowangi, Ds. Sumberanyar, Ds. Watukebo, and surrounding |
Profession | : | Pemasangan GSW (Ground Steel Wire) pada Jaringan SUTM (Medium Voltage Air Line) 20.000 Volt - Baluran feeder |
Work Area | : | PLN Unit Layanan Pelanggan Banyuwangi Kota |
When the job is finished before the hour 16.00 WIB, then the flow of electric power will be normalized again. | ||
Day / Date | : | Thursday, 24 October 2019 |
Jam | : | 09:00 - 16:00 WIB |
Location of Padam | : | Ds. Yosomlyo (sebagian), Ds. Wringinrejo (sebagian), Ds. Greed, Ds. Sumbersari, and surrounding |
Profession | : | SUTM Network Maintenance (Medium Voltage Air Line) 20.000 Volt - Pandan feeder & Tembokrejo feeder |
Work Area | : | PLN Unit Layanan Pelanggan Genteng |
When the job is finished before the hour 16.00 WIB, then the flow of electric power will be normalized again. | ||
Day / Date | : | Thursday, 24 October 2019 |
Jam | : | 08:30 - 16:00 WIB |
Location of Padam | : | Ds. Yosomlyo, Ds. Wringinagung, and surrounding |
Profession | : | Rehab Jaringan SUTM (Medium Voltage Air Line) 20.000 Volt - Feeder Jajag |
Work Area | : | PLN Unit Layanan Pelanggan Jajag |
When the job is finished before the hour 16.00 WIB, then the flow of electric power will be normalized again. | ||
When it comes to the clock 11.00 WIB there is no blackout, means the blackout is cancelled. | ||
Source : https://www.facebook.com/plnup3banyuwangi/, For information or service complaints, please go directly to the PLN Contact Center 123 or through the PLN MOBILE application. |