INFORMATION OF ELECTRICITY NETWORK RELIABILITY IMPROVEMENT PT. PLN (PERSERO) UP3 BANYUWANGI |
||
---|---|---|
Day / Date | : | Friday, 20 August 2021 |
Jam | : | 09.00 s/d 13.00 WIB |
Location of Padam | : | Part of Jl. Raden Wijaya, Jl. Kenari, Jl. Akasia, Lingkungan Payaman dan sekitarnya |
Profession | : | Penggantian Konduktor pada Jaringan SUTM (Medium Voltage Air Line) 20.000 Volt - Penyulang Giri |
Work Area | : | PLN ULP Banyuwangi City |
Source : https://www.facebook.com/plnup3banyuwangi/, For information or service complaints, please go directly to the PLN Contact Center 123 or through the PLN MOBILE application. | ||
- When the job is completed before the hour has been determined, then the flow of electric power will be normalized again. | ||
- When it comes to the clock 11.00 WIB there is no blackout, means the blackout is cancelled. | ||